How to Specify Steel Site Hoarding Panels

Order solid steel hoarding as a complete perimeter system. Sheet, frame, supports, connectors and gates belong on the same drawing because they all affect how the line transfers wind loads.

Panels

The panel forms the face. Common constructions are profiled or flat steel sheet in a tube frame, plywood or composite sheet on timber or steel framing, and moulded plastic panels for short-term work.

Accessory Interfaces

Accessories are added after the structure is designed and are the usual cause of overload or obstruction. Each should be treated as an interface with a stated limit.

ConnectionLoad carried
Panel to panelAlignment; shear between panels; continuity of face
Panel to post or frameFull wind reaction from the panel
Stay to panel and to ballastTension or compression in the stay
Base to groundHorizontal shear and uplift

Supports and the Stability Calculation

Supports carry the wind force to the ground. Three arrangements are used: free-standing frames with counterweights, back-stays to ballast or anchors, and posts fixed into the ground or onto an existing slab.

Lifting and Manual Handling

Mass is only part of the problem. A panel is too wide to hold close to the body, has few places to grip, and catches the wind.

Wind during handling is the hazard specific to hoarding. A solid panel held upright is a sail.

Work with solid panels should therefore stop at a stated wind speed, set in the method statement and measured on site with a hand-held anemometer. A limit in the region of 8 m/s to 10 m/s in gusts is typical for manual handling of standard panels, and lower for large panels and for lifting by crane. Panels should be carried edge-on to the wind where possible and never left free-standing.

Connections

Connections join panel to panel, panel to support, and support to ground or ballast.

Access

Structural continuity: the posts on each side of an opening carry the wind load of the adjacent panel without help from a neighbour, plus the weight and wind load of the gate leaf. They normally need heavier sections and their own restraint.

Visibility: a solid face hides pedestrians from drivers leaving the site.

Sharp Edges

Edges left exposed on the public side are a hazard to passers-by for the life of the hoarding.

HazardWhere
Sheet edgesPanel perimeter if not folded or capped; sheet ends at laps
Site-cut sheet and offcutsAround openings, closures and trimmed panels
Tube ends and bracketsPosts, stays, frames
Zinc spikes and weld spatterGalvanized frames
Exposed fastener pointsScrew tips through the back of frames

Safe Sequence of Installation

Before starting: exclusion zone and pedestrian management in place; wind speed measured and below the limit; delivery checked; storage stable; crew briefed on the sequence and on the stop conditions.

End of each work period: no free end left unbraced; no panels left leaning; offcuts, swarf and banding removed; public side checked for edges and projections.

Openings and gates: posts on both sides stabilised independently before the gate leaf is hung.

Dismantling: the reverse order, panel by panel, with each panel held before its last connection is undone; never by pulling a run over.

How the Subsystems Influence the Outcome

AccessoryInterface with the system
Graphics and printed wrapsFixed to the face; no added wind area on a solid face
Signs and banners above the top edgeIncrease height and overturning moment
Lighting and cable runsMounted on posts or top rail
Vision panels and letter boxesOpenings in the face sheet

Information for a Complete Specification

  • Site: location, exposure, design wind speed and the period of installation; ground surface and whether fixing into it is permitted.
  • Geometry: height, total length, corners and returns, and the width available behind the face for stays and ballast.
  • Panels: face material and thickness, frame, finish and colour, and the requirement for a closed bottom edge.
  • Access and accessories: number and clear width of doors and gates, vision panels, and any signs, lighting or overhead protection to be carried.
  • Verification: design calculation or test evidence for stability and infill rigidity to the adopted standard, with installation and inspection instructions.

Price the difficult bay first

A short bay beside a driveway may need more coordination than a long straight run. Draw the solid face, sightline, opening and space behind the fence together. Ask bidders to price the transition, the gate supports and the narrower working area as explicit items.

Frequently asked questions

What drawing should I request for steel site hoarding?

Ask for a bay elevation and a section through the supports, showing panel joints, the ground interface, fixings and transitions at gates and corners.

Can a steel hoarding bay be ordered before the support design is approved?

You can price a provisional bay. Release the order after confirming the support arrangement for the site exposure, bearing surface and clearances.